A can do a work in 15 days and B in 20 days. If they together work on it for 4 days; what fraction of the work will be left? A's 1-day work = `1/15` B's 1-day work = `1/20` (A+B)'s 1-day work =`1/15+1/20` `=(4+3)/60=7/60` (A+B)'s 4 days work =`7/60xx4=7/15` Remaining work =`1-7/15=(15-7)/15` `=8/15` Is there an error in this question or solution?